UConn HomeBanner
HOME UPDATES CONSTRUCTION REPORTS TIMELINE STATUS PROJECT MAPS INVOLVEMENT   

 

Timeline

 

Closure Construction Schedule

The dates below are targets for the start and completion of all the elements of the project.   Weather and other factors can affect progress, so please check back for updates as the work continues.

Closure Schedule, UConn Landfill 
Construction Task Start Date Completion Date
Preparation of Bid Documents Completed Completed
Hire Project Construction Management Completed Completed
Review Contractor Submittals Completed Completed
Mobilization, Site Preparation, and Stormwater/Erosion Control Jul-06  
Construction of the leachate interceptor trenches (LITs) Nov 06 Jan-07
Contaminated Sediment Removal and Relocation Sept-06 Oct-06
Waste Consolidation Sept-06 Oct-06
Landfill Reshaping and Grading June-07 July-07
Installation of Monitoring Wells Dec-06 Dec-06
Cover System Installation Aug-07 Oct-07
Road and Parking Lot Construction Oct-07 Dec-07
Closeout ­ Project Completion and Demobilization     Dec-07
Preparation of closure certification report
Following Project Closeout
90 - 120 Days Following Project Closeout

 

 

      
USEFUL LINKS         LANDFILL PROJECT HOME         TEXT-ONLY UConn Landfill Project
Disclaimers, Privacy, & Copyright
Contacts