The dates below are targets for the start and completion of all the elements of the project. Weather and other factors can affect progress, so please check back for updates as the work continues.
| Closure Schedule, UConn Landfill |
| Construction Task |
Start Date |
Completion Date |
| Preparation of Bid Documents |
Completed |
Completed |
| Hire Project Construction Management |
Completed |
Completed |
| Review Contractor Submittals |
Completed |
Completed |
| Mobilization, Site Preparation, and
Stormwater/Erosion Control |
Jul-06 |
|
| Construction of the leachate interceptor trenches (LITs) |
Nov 06 |
Jan-07 |
| Contaminated Sediment Removal and Relocation |
Sept-06 |
Oct-06 |
| Waste Consolidation |
Sept-06 |
Oct-06 |
| Landfill Reshaping and Grading |
June-07 |
July-07 |
| Installation of Monitoring Wells |
Dec-06 |
Dec-06 |
| Cover System Installation |
Aug-07 |
Oct-07 |
| Road and Parking Lot Construction |
Oct-07 |
Dec-07 |
| Closeout Project Completion and Demobilization |
|
Dec-07 |
| Preparation of closure certification report |
Following Project
Closeout |
90 - 120 Days
Following Project Closeout |